Home / Research / AI Data Center Construction Deaths and Injuries Statistics

AI Data Center Construction Deaths and Injuries Statistics: 2026 Report

Our analysts compiled every death and injury at a US data center construction site that we could confirm in a primary record or a news report we opened directly. We searched OSHA's Severe Injury Reports file, which runs from January 2015 to November 2025, for addresses and employer descriptions tied to data center projects. We then added deaths and injuries from local news, court filings, and state OSHA letters, and compared the results with Bureau of Labor Statistics figures for construction overall.

Key Findings

  • We documented 8 deaths and 11 injuries at US data center construction sites from September 2019 to October 2026, a minimum count because no government dataset identifies these projects.
  • Ten of the 19 documented incidents happened in 2025, including 4 deaths, after no more than one a year in the earlier years on record.
  • Vehicles and mobile equipment caused 3 of the 8 deaths, the most of any cause, and falls caused 2.
  • The two federal OSHA penalties we confirmed at Stargate in Abilene, Texas, were proposed at $26,674 and settled at $13,000 in total.
  • US construction workers died at a rate of 9.2 per 100,000 full-time equivalent workers in 2024, 2.8 times the rate of 3.3 for all workers.

The race to build AI computing capacity has turned farmland and industrial parks in Texas, Georgia, Ohio, Indiana, and Tennessee into sprawling construction sites. At Stargate's first campus in Abilene, Texas, Oracle told TIME that about 8,000 people had worked 20 million hours. Some of the workers on these projects did not go home. Since 2025, local news outlets, court filings, and safety regulators have recorded deaths at data center sites built for Amazon, Meta, xAI, QTS, Vantage, and others. No federal dataset counts those losses, so we built one.

In the following sections, we break down deaths and injuries by year, state, cause, site operator, and contractor, then look at OSHA inspections and penalties at data center sites and at how data center incidents compare with fatality and injury rates for construction as a whole.

Why Every Count Here Is a Minimum

Before any totals, it helps to know what public records can and cannot show about these sites.

OSHA's data does not flag data centers. Construction employers report under codes such as NAICS 236220 (commercial and institutional building) or 238210 (electrical contractors), the same codes used for hospitals, schools, and warehouses. A data center injury appears in OSHA files only when the address or narrative happens to identify the project. Many reports give only a street address or a description such as "jobsite" (Source 2).

The Severe Injury Reports file also covers only states where federal OSHA has jurisdiction. Indiana, Tennessee, and Virginia run their own state plans, so injuries at data center sites in those states do not appear in it (Source 2). The file ends Nov. 30, 2025, and it records hospitalizations, amputations, and eye losses, not deaths. OSHA's fatality records were not machine-readable for us: the agency's inspection search returned access errors, its fatality page is an embedded dashboard, and the Labor Department's enforcement API requires a registered key.

Deaths that never reach the news also cannot be counted here. That means the 19 incidents in our dataset, including 8 deaths, are a floor, not an estimate of the true toll.

Key Findings

Data Center Construction Deaths and Injuries by Year

Counting incidents by the year they happened shows when the documented toll rose.

Our dataset holds 19 incidents from September 2019 to September 2026: 8 deaths and 11 injuries (Source 1). Of the 11 injuries, 7 come from OSHA Severe Injury Reports, each involving a worker who was hospitalized. The other 4 come from TIME's review of lawsuits, an Indiana OSHA letter, and local news.

Documented deaths and injuries at US data center construction sites by year of incident

YearDeathsInjuriesTotal
2019011
2021011
2024011
20254610
2026 (through Oct 22)224
Year not reported202
Total81119

Source: AI Industry Reviews incident dataset (Source 1). Deaths are counted in the year of the incident. Alexis Vicent was injured in August 2025 and died in February 2026.

Deaths and injuries at US data center construction sites by year

Source: AI Industry Reviews analysis of OSHA Severe Injury Reports, state OSHA records, court filings, and local news, data through Oct 22, 2026 (Source 1).

Key Findings

The Workers Who Died

Each of the eight deaths we confirmed is listed below, with what the public record says about how it happened.

Deaths at US data center construction sites, 2025 to 2026

Date of incidentWorkerSiteStateWhat happenedContractor or employer
Apr 10, 2025Not identifiedVantage campus, AshburnVATrench collapseNot identified; HITT Contracting sign at site
Jun 28, 2025Anthony J. Riera Azuaje, 25QTS campus, FayettevilleGAElectrocuted on a scissor lift; died Jul 2Andrew Electric
Aug 15, 2025Alexis VicentxAI Colossus II, MemphisTNFell 25 to 30 ft from a mezzanine on his first day; died Feb 26, 2026Suit names CTC Property, MZX Tech, and Omega Foundation Services
Oct 6, 2025Maurice McGowan, 28Rowan Digital Infrastructure Cinco campus, Medina CountyTXStruck by an articulating truckTurner Construction, general contractor
Mar 20, 2026Omar Egues Montero, 61Haydon AI Data Center, Haskell CountyTXRun over while a bulldozer pushed a stuck semi-truck freeNot reported
Sep 14, 2026Christopher Lawe, 33Meta data center, LEAP district, LebanonINStruck by a pickup truck on siteMortenson
Not reportedNot identifiedAmazon, Industrial Parkway, Jerome TownshipOHFell to his deathNot reported
Not reportedNot identifiedAmazon, Warren Road, Jerome TownshipOHCrushed to death during constructionNot reported

Sources: Loudoun Times-Mirror (Source 11); Data Center Dynamics (Sources 4, 5, and 12); Action News 5 (Source 8); KSAT and ENR (Sources 6 and 7); KTXS (Source 9); ENR (Source 10).

Anthony Riera Azuaje contacted energized wires or conduit while working on a light fixture from a scissor lift. His family has sued Allison-Smith Company over the temporary power fittings and grounding at the site (Sources 4 and 5). Alexis Vicent's family filed a wrongful-death suit on Sept. 11, 2026, seeking $30 million (Source 8). Christopher Lawe, a married father of two from Ponca City, Oklahoma, was struck by a Mortenson pickup carrying workers at the end of the day, and Mortenson temporarily halted work (Source 10).

Key Findings

Deaths and Injuries by State

Where an incident happened also shapes whether it gets recorded, because some states keep their own injury files.

Texas has the most incidents, with 7, driven by five injuries at Stargate in Abilene and two deaths elsewhere in the state (Source 1).

Documented incidents by state

StateDeathsInjuriesTotalIn federal OSHA injury reports
Texas257Yes
Georgia134Yes
Ohio213Yes
Indiana112No (state plan)
Virginia101No (state plan)
Tennessee101No (state plan)
Oklahoma011Yes

Source: AI Industry Reviews incident dataset (Source 1); OSHA Severe Injury Reports coverage (Source 2).

Data center construction deaths and injuries by state

Source: AI Industry Reviews analysis of OSHA Severe Injury Reports, state OSHA records, court filings, and local news, data through Oct 22, 2026 (Source 1).

Key Findings

Deaths and Injuries by Cause

Sorting the incidents by how each worker was hurt, using the event groups BLS uses for its fatality census, shows which hazards to plan for.

We assigned each incident to a BLS event group from the description in the source record. Where the record did not say how the injury happened, we coded it as not determinable (Source 1).

Documented incidents by cause

Cause (BLS event group)DeathsInjuriesTotal
Falls, slips, trips246
Contact with objects and equipment156
Transportation incidents (vehicles and mobile equipment)303
Exposure to harmful substances or environments (electrocution)101
Overexertion011
Not determinable112
Total81119

Source: AI Industry Reviews incident dataset (Source 1).

Key Findings

Deaths and Injuries by Site Operator and Contractor

Grouping the incidents by the company building or leasing each campus, and by the contractors named in the records, shows where responsibility sits.

Stargate in Abilene, developed by Crusoe for Oracle and OpenAI, has the most documented incidents at a single campus, with 5 injuries. Andre Guthrie, 61, was found dead at the first Abilene site on Oct. 1, 2025; DPR said his death was unrelated to workplace conditions, police were awaiting autopsy results, and OSHA told TIME it was "not aware" of the fatality. We did not count his death (Sources 1 and 3).

Contractors and employers involved in documented incidents

Contractor or employerRole in recordSiteOutcome
DPR ConstructionEmployer cited by OSHA; defendant in a suitStargate, Abilene TX2 injuries
Abilene Glass & MirrorEmployerStargate, Abilene TX1 injury
Ruiz-Boyter Construction & SuppliesEmployer cited by OSHAStargate, Abilene TX1 injury
Kiewit (The Industrial Company) and MMR GroupDefendants in a suitStargate, Abilene TX1 injury
Turner ConstructionGeneral contractorRowan Cinco, Medina County TX1 death
MortensonGeneral contractor and employerMeta, Lebanon IN1 death
Andrew ElectricEmployerQTS, Fayetteville GA1 death
Allison-Smith CompanyDefendant in a suitQTS, Fayetteville GA1 death
CTC Property, MZX Tech, and Omega Foundation ServicesDefendants in a suitxAI Colossus II, Memphis TN1 death
Genius Roof, with Blydan (GC) and Phoenix ConstructionGenius Roof cited by Indiana OSHAProject Maize, Michigan City IN1 injury
AZZ Incorporated Enclosure SystemsEmployerQTS, Atlanta GA1 injury
The Superior GroupEmployerAWS, New Albany OH1 injury
Lewis Electrical ContractorsEmployerDataBank ATL 4, South Fulton GA1 injury
Liberty Steel PlacersEmployerGoogle, Pryor OK1 injury

Sources: OSHA Severe Injury Reports (Source 2); TIME (Source 3); DCD (Sources 4 and 5); KSAT and ENR (Sources 6, 7, and 10); Action News 5 (Source 8); Indiana OSHA (Source 13).

Data center construction deaths and injuries by site operator

Source: AI Industry Reviews analysis of OSHA Severe Injury Reports, state OSHA records, court filings, and local news, data through Oct 22, 2026 (Source 1).

Key Findings

OSHA Inspections, Citations, and Penalties at Data Center Sites

Inspections and penalties are the main public check on these sites, so we collected every regulatory action we could confirm.

We confirmed two federal OSHA penalties, one Indiana OSHA citation and one Tennessee OSHA finding. Together, the two federal penalties were proposed at $26,674 and settled at $13,000 (Sources 3 and 13).

Confirmed OSHA and state OSHA actions at data center construction sites

SiteEmployerIncidentActionProposed penaltyFinal penalty
Stargate, Abilene TXDPR ConstructionWorker pinned under a mini excavator, May 23, 2025Inspection 1829462; citation for training on excavator hazards, withdrawn in settlement$5,674$0
Stargate, Abilene TXRuiz-Boyter Construction & SuppliesWorker struck by a slipping pipe jack and fell from a ladder, Jul 28, 2025Inspection 1842360; unsafe jack-and-pole equipment, penalty reduced for good faith$21,000$13,000
Stargate, Abilene TXAbilene Glass & MirrorGlass panels fell on a worker's leg, May 30, 2025OSHA accepted the employer's response and closed the probe a month laterNone reportedNone reported
Project Maize, Michigan City INGenius RoofReported roof fall, Oct 9, 2025Indiana OSHA inspection 1857455; citation for failing to evaluate walking-working surfacesNot stated in letterNot stated in letter
xAI Colossus II, Memphis TNNot statedFall of Alexis Vicent, Aug 15, 2025Tennessee OSHA found he was not adequately protected from fall hazards, per the family's suitNot reportedNot reported

Sources: TIME (Source 3); Indiana OSHA letter of Jan. 22, 2026 (Source 13); Action News 5 (Source 8). Inspection numbers for the Abilene cases come from OSHA Severe Injury Reports (Source 2).

Debbie Berkowitz, a former OSHA adviser, told TIME it was "highly unusual for OSHA to vacate a citation, especially when the settlement agreement confirms there was a hazard that the company agreed to abate" (Source 3).

In Indiana, the inspection came after a complaint from Local 150 of the operating engineers union. The complaint cited police video of a worker who "reportedly fell nearly 70 feet" from the roof. Indiana OSHA found no evidence that the worker struck his head, but it did cite the roofing employer (Source 13).

Key Findings

How Data Center Incidents Compare With Construction Overall

National figures for all US construction give the data center incidents a baseline.

Construction is one of the most dangerous industries in the country. In 2024, 1,034 construction workers died from work injuries, a fatal injury rate of 9.2 per 100,000 full-time equivalent workers, compared with 3.3 for all workers (Sources 15 and 16).

Fatal work injuries in 2024, construction and related industries

GroupDeaths, 2024Fatal injury rate per 100,000 FTE
All workers5,0703.3
Construction1,0349.2
Construction of buildings (NAICS 236)220Not shown
Nonresidential building construction (NAICS 2362)75Not shown
Commercial and institutional building (NAICS 23622)58Not shown
Electrical contractors (NAICS 23821)59Not shown

Sources: BLS Census of Fatal Occupational Injuries, 2024 (Sources 15, 16, and 17). BLS publishes detailed industry rates only in spreadsheet form, so we report counts for those rows.

Fatal work injury rates by industry, 2024

Source: US Bureau of Labor Statistics, Census of Fatal Occupational Injuries, 2024 (Sources 15 and 16).

Key Findings

Construction fatal injuries by event, 2024

EventDeathsShare of construction deaths
Falls, slips, trips38937.6%
Transportation incidents24423.6%
Exposure to harmful substances or environments18718.1%
Contact with objects and equipment16115.6%
Violence and other injuries by persons or animals464.4%
Fires and explosions50.5%

Source: BLS CFOI 2024, table A-1 (Source 17). Shares are our calculation from the reported counts; the six events sum to 1,032 of the 1,034 deaths.

How US construction workers died on the job in 2024

Source: US Bureau of Labor Statistics, Census of Fatal Occupational Injuries, table A-1, 2024 (Source 17).

Key Findings

Nonfatal Injury Rates and Severe Injury Reports

Nonfatal injury rates and OSHA's severe injury reports show how often construction workers are hurt without being killed.

BLS reported 2.2 recordable injury and illness cases per 100 full-time workers in construction in 2024, against 2.3 for all private industry. Construction's rate of cases with days away from work, job restriction, or transfer was 1.3 (Sources 18 and 19).

Nonfatal injury and illness rates, 2024

GroupTotal recordable cases per 100 FTE
Private industry2.3
Construction2.2
Nonresidential building construction (NAICS 2362)1.9
Electrical contractors (NAICS 23821)1.8

Source: BLS Survey of Occupational Injuries and Illnesses, 2024, table 1 (Source 19).

OSHA severe injury reports, construction and commercial building, 2015 to 2025

YearConstruction (NAICS 23)Commercial and institutional building (NAICS 236220)
20151,711174
20161,867207
20171,862204
20181,969199
20191,956219
20201,729181
20211,528155
20221,516135
20231,626167
20241,618149
2025 (Jan to Nov)1,639168

Source: AI Industry Reviews count of OSHA Severe Injury Reports by employer NAICS code, federal OSHA states only (Source 2).

Key Findings

What Data Center Construction Safety Figures Mean for Workers and Developers

The documented record shows at least 8 workers killed and 11 injured while building US data centers, with 14 of the 17 dated incidents in 2025 or 2026. The causes are the familiar ones in construction: vehicles and equipment moving among workers on foot, falls from height, a trench wall, and an energized line. What is different is the size of the AI campuses: some 8,000 people have worked at Stargate's first Abilene campus alone (Source 3).

The record is also thin by design. OSHA does not tag data center projects, three of the states in our dataset keep their injury reports out of the federal file, and fatality records sit behind interfaces that cannot be searched in bulk. The two federal penalties we confirmed for serious injuries at Stargate ended at $13,000 in total.

So if you are a developer, contractor, or local official approving an AI campus, ask for site-level injury data, traffic plans, and fall protection plans before work starts, and make them public when incidents happen.

Data Collection and Methodology

Scope. The dataset covers deaths and injuries to workers at US sites where a data center was under construction, from September 2019 through Oct 22, 2026. It includes workers employed by contractors and delivery drivers injured on site. It excludes operating data centers, factories that make data center equipment, off-site road crashes, and incidents outside the US.

OSHA Severe Injury Reports. We searched the full OSHA file of 105,996 reports from January 2015 to November 2025 for data center operators, project names, and addresses known to belong to data center construction sites, then read each narrative. We kept a report only when the address or narrative tied it to a data center project and the employer was doing construction work. The file covers federal OSHA states and records hospitalizations, amputations, and eye losses; it does not record deaths.

Other sources. Deaths and injuries from news reports, court filings, and state OSHA letters were included only after we opened the page or document directly. We did not use facts that appeared only in search engine summaries. Where a page was paywalled, we used only the text visible to us or another outlet's attributed report.

Access limits. OSHA's inspection and fatality search pages returned access errors, OSHA's fatality page is an embedded dashboard, and the Labor Department's enforcement data API requires a registered key, which we did not obtain. Penalty amounts therefore come from TIME's review of OSHA files and from the Indiana OSHA letter, and inspection numbers from the Severe Injury Reports file.

Classification. Causes follow the BLS event groups used in the fatality census, assigned from each source's description. Incidents without a described cause are coded as not determinable. Years are the year of the incident, not the year of death.

Comparisons. BLS fatality and injury figures are for 2024, the latest year published. We did not calculate a fatality rate for data center construction, because no source reports total hours worked on these sites. Shares are our calculations from the reported counts.

Dropped figures. We did not use a fatal injury rate for NAICS 236220 because BLS publishes it only in a spreadsheet we could not check, and we did not use a 2020 to 2023 construction fatality rate trend that appeared only in search summaries. We left out the dates of the two Ohio deaths, a court case number for the QTS suit, a claim about the general contractor at the QTS Fayetteville campus, an attribution of the Project Maize roof fall to a specific worker, and the penalty amount for the Indiana citation, because none appeared in a source we could open. We did not count the death of Andre Guthrie at Stargate, the death of a dump truck driver off site near Meta's Hyperion campus, or deaths at data center sites outside the US. We also excluded an amputation at a Schneider Electric modular data center facility in Red Oak, Texas, and a 2020 amputation during maintenance at CyrusOne's operating facility in Norwalk, Connecticut.

Money. Penalties are in US dollars as reported.

Sources

  1. AI Industry Reviews analysis of deaths and injuries at US data center construction sites, conducted November 2026, drawing on OSHA Severe Injury Reports, state OSHA records, court filings, and local news from September 2019 to October 22, 2026.
  2. OSHA, Severe Injury Reports, January 2015 to November 2025 data file. osha.gov
  3. TIME, "Broken Bones, Lawsuits, and NDAs: Inside the Worker Safety Concerns at Stargate Data Center," Jun 25, 2026. time.com
  4. Data Center Dynamics, "Construction worker passes away after electrocution at QTS Georgia data center," Jul 16, 2025. datacenterdynamics.com
  5. Data Center Dynamics, "Lawsuit launched after death of construction worker at data center site in Fayetteville, Georgia," Sep 25, 2025. datacenterdynamics.com
  6. KSAT, "Authorities ID worker killed at data center construction site in Medina County," Oct 10, 2025. ksat.com
  7. ENR, "Worker Identified in Fatal Turner Construction Data Center Accident," Oct 10, 2025. enr.com
  8. Action News 5, "Family files wrongful death suit one year after worker's fatal fall at SpaceX/xAI data center," Sep 22, 2026. actionnews5.com
  9. KTXS, "Haskell AI data center worker killed in accident," Mar 25, 2026. ktxs.com
  10. ENR, "Worker Killed at Meta Data Center in Indiana," Sep 17, 2026. enr.com
  11. Loudoun Times-Mirror, "Worker killed in Ashburn trench collapse," Apr 12, 2025. loudountimes.com
  12. Data Center Dynamics, "Amazon data centers in Jerome Township, Ohio, called emergency services 84 times since 2021," Sep 29, 2025, citing The Columbus Dispatch. datacenterdynamics.com
  13. Indiana Occupational Safety and Health Administration, letter to complainant re Genius Roof, inspection 1857455, Jan 22, 2026 (published by IUOE Local 150). local150.org
  14. Atlanta News First, "Construction worker badly injured at Google data center site in LaGrange," Apr 4, 2026. atlantanewsfirst.com
  15. US Bureau of Labor Statistics, "National Census of Fatal Occupational Injuries in 2024," Feb 19, 2026. bls.gov
  16. US Bureau of Labor Statistics, "Number and rate of fatal work injuries, by industry sector," CFOI chart data, 2024. bls.gov
  17. US Bureau of Labor Statistics, CFOI table A-1, fatal occupational injuries by industry and event or exposure, 2024. bls.gov
  18. US Bureau of Labor Statistics, "Employer-Reported Workplace Injuries and Illnesses, 2024," Jan 22, 2026. bls.gov
  19. US Bureau of Labor Statistics, SOII table 1, incidence rates of nonfatal occupational injuries and illnesses by industry, 2024. bls.gov
  20. Louisiana Illuminator (Gulf States Newsroom), "Construction on Meta's largest data center brings 600% crash spike, chaos to rural Louisiana," Nov 22, 2025. lailluminator.com